Scope of Work Labor ONLY

Property is located around 79th California 
  1. Demo and debris removal of old kitchen cabinets, hardware, countertops and flooring.

  2. Remove soffits if possible

  3. Install 10 new kitchen (Gray Shaker cabinets) cabinets.

  4. Install Backsplash

  5. Install new sink,

  6. faucet fixtures 

  7. hardware (Cabinet Nobs)

  8. Install new Ceramic Flooring 

  9. New GFCI outlets installed at the countertops

  10. Pluming: P-trap, waterline, baskets and valves.

  11. Paint living room, kitchen,

  12. Install new 5 1/4 baseboards, door and window trim

  13. Install a new pre-hung back door

  14. Install 1 circuit breaker to move the microwave to a different breaker to prevent popping.

  15. Install garbage disposal

  16. Install waterlines for the dishwasher and fridge

  17. Need an outlet for the microwave over the stove.

  18. Install new double pane window with (aluminum capping if needed)

  19. Remove the wall to open the kitchen to the dining room. Install a 48" island with countertop and area for seating in that opening.

  20. Install a beam as support the ceiling

  21. Install 2 pendant lights at the island

  22. Move the electrical and ductwork in the wall.

Kitchen Materials

Screen Shot 2021-09-23 at 2.08.21 PM.png

Kitchen Before Pictures

Screen Shot 2021-09-23 at 2.10.56 PM.png
Screen Shot 2021-09-23 at 2.10.06 PM.png
Screen Shot 2021-09-23 at 2.10.23 PM.png
Screen Shot 2021-09-23 at 2.10.15 PM.png
bottom of page